HomeAbout usOur historyOur missionCertificationsSolar energyGuaranteed energy outputProjectsTensovoltaicoCable-mounted projectsPraesidium Partner ProgramTrust PVInsurance and warrantiesInsightsIncentives and grantsContact
Insights · Solar PV

Revamping or repowering: two different upgrades for business solar PV

One brings your system back to its original performance, the other boosts its size and output. How they differ and when you need each.

Revamping and repowering are often used interchangeably, but they’re two different things. Revamping brings an existing system back to the performance it was designed for; repowering increases its capacity and output. Which one you need depends on two things: how much the system produces today compared with what it should, and how much energy your company uses today compared with when the system went in.

Revamping: win back what you’ve lost. Over 10–15 years, modules lose 5–12% of their yield (0.5–0.8% a year), and inverters reach the end of their life. Revamping restores the system to its design performance without changing its size: the inverter, modules with hot spots or micro-cracks, cabling and monitoring are replaced.

Repowering: produce more than ever before. Today’s modules exceed 21% efficiency, against 15% ten years ago. You can fit about 40% more capacity on the same roof – and more still by using spare surfaces, for example with the cable-mounted system. It’s the right move when your company uses more energy than when the system was installed.

RevampingRepowering
GoalRestore original performanceIncrease capacity and output
Installed capacityUnchangedIncreases
Typical workReplacement of inverter, faulty modules, cables, monitoringNew high-efficiency modules, new surfaces, properly sized inverter and storage
When it’s neededFalling output, frequent faultsHigher consumption, undersized system
Ongoing incentives (Conto Energia)Retained, following GSE proceduresRetained on the original part; the added capacity is not covered by Conto Energia
InvestmentModerateHigher, with more energy produced

Output falling and consumption rising at the same time? Then do both in one go: one site, one set of paperwork.

If the system still earns Conto Energia (Italy’s former feed-in tariff), the paperwork matters as much as the work itself. Significant changes must be reported to the GSE within 60 days of completion, and old components must be disposed of as WEEE. One mistake can cost you the tariff.

Is your system a few years old?

Ask us which upgrade makes sense.

Free roof assessment
Free roof assessment